Q1. An activity in a network diagram is said to be —- if the delay in its start will further delay the project completion time.
- Critical activity
- Dummy activity
- Forward pass
- Null activity
Answer:- Critical activity
Q2. In PERT analysis the maximum time that is required to perform the activity under extremely bad conditions is known as —-.
- Normal time
- Optimistic time
- Pessimistic time
- Most likely time
Answer:- Pessimistic time
Q3. What is the PERT time (Te) with optimistic, most likely and pessimistic time estimations of 6, 10, 14 days.
- 5
- 10
- 7
- 12
Answer:- 10
Q4. In PERT what type of distribution is used for time estimation?
- Beta distribution
- Poisson distribution
- Exponential distribution
- Chi Square
Answer:- Beta distribution
Q5. The difference between the maximum time available and the actual time needed to perform an activity is known as …..
- Free float
- Independent float
- Total float
- Half float
Answer:- Total float
Q6. Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be
- 1
- 6
- 12
- 18
Answer:- 1
Q7. A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
- 3
- 9
- 81
- 27
Answer:- 9
Q8. Critical activities have
- Maximum float
- Minimum float
- Zero float
- Negative float
Answer:- Zero float
Q9. Total float of an activity is difference between
- Early Finish and Late Finish
- Free Float and Interference Float
- Duration and Early Start
- Independent Float and the Activity
Answer:- Early Finish and Late Finish
Q10. If the variance of a critical path is 25 days, the standard deviation of that critical path is
- 12.5 days
- 15 days
- 0 days
- 5 days
Answer:- 5 days