Q1. Which of the following is a cost estimating technique?
- Variance management
- Cost aggregation
- Parametric estimating
- Cost change control system
Answer:- Parametric estimating
Q2. A cost performance index value greater than 1.0 signifies:
- Cost underrun
- Cost overrun
- Cost run equal
- None of the above
Answer:- Cost underrun
Q3. Schedule value is termed as:
- Earned value – Actual value
- Earned value – Planned value
- Actual cost – planned value
- Actual cost – Earned value
Answer:- Earned value – Planned value
Q4. Cost performance index is calculated by using:
- Actual cost / Planned value
- Planned value / Earned value
- Budget cost at completion / Actual cost
- Earned value / Actual cost
Answer:- Earned value / Actual cost
Q5. Which of the following is not used to provide performance measurement of any work at a given point of time.
- Planned value
- Budgeted cost at completion
- Earned value
- Actual cost
Answer:- Budgeted cost at completion
Q6. Which of the following is not a cost budgeting input?
- Project scope statement
- WBS Dictionary
- Resource calendar
- Performance reports
Answer:- Performance reports
Q7. Which of the following is not a cost control technique?
- Reserve analysis
- Project performance reviews
- Forecasting
- Variance management
Answer:- Reserve analysis
Q8. Cost value can be regarded as:
- Earned value – Actual cost
- Earned value – Planned value
- Planned value – Actual cost
- Planned value – Earned value
Answer:- Earned value – Actual cost
Q9. Estimating the cost of individual work packages or individual schedule activities with the lowest level of detail is called?
- Parametric Estimating
- Bottom-up Estimating
- Vendor Bid Analysis
- Reserve Analysis
Answer:- Bottom-up Estimating
Q10. Which one of the following is not a dimension of Quality?
- Performance
- Reliability
- Cost
- Durability
Answer:- Cost