Q1. In PERT, the distribution of an activity time is assumed to be: 

  • Normal distribution
  • Gamma distribution
  • Beta distribution
  • Exponential distribution
Answer:- Beta distribution

Q2. The latest start time can be regarded as 

  • LFT – duration of activity 
  • LFT + duration of activity
  • EFT – duration of activity
  • EFT + duration of activity
Answer:- LFT - duration of activity 

Q3. Which of the following statement is false in crashing networks? 

  • Direct cost decreases as project duration decreases
  • Direct cost increases as project duration decreases
  • Direct cost decreases as project duration increases
  • Direct cost increases as project duration increases
Answer:- Direct cost increases as project duration decreases

Q4. An act (i, j) as critical if and only if 

  • Total float = 0 
  • Free float = 0
  • Independent float = 0 
  • All of the above 
Answer:- All of the above 

Q5. In a PERT network, the slack of an event is the difference between: 

  • Latest occurrence time and earliest occurrence time 
  • Latest occurrence time and earliest finish time 
  • Earliest occurrence time and latest occurrence time
  • Earliest occurrence time and latest finish time
Answer:- Latest occurrence time and earliest occurrence time 

Q6. In the CPM network critical path denotes the 

  • Path where maximum resources are used 
  • Path where minimum resources are used 
  • Path where delay of one activity prolongs the duration of completion of a project 
  • Path that gets monitored automatically 
Answer:- Path where delay of one activity prolongs the duration of completion of a project 

 Q7. The earliest finish time can be regarded as 

  • EST + duration of activity 
  • EST – duration of activity
  • LFT + duration of activity 
  • LFT – duration of activity 
Answer:- EST + duration of activity 

Q8. The essential condition for the decompression of an activity is:

  • The project time should change due to decompression
  • After decompression the time of an activity invariably exceeds its normal time
  • An activity could be decompressed to the maximum extent of its normal time
  • None of the above
Answer:- An activity could be decompressed to the maximum extent of its normal time

Q9. Crashing of a project is the process of reducing the _________________________ of the project? 

  • Cost
  • Time
  • Material 
  • Labor
Answer:- Time

Q10. Float is used for __________. 

  • Activities 
  • Events
  • Nodes 
  • None of the above 
Answer:- Activities 