NPTEL Project Management For Managers Week 10 Assignment Answers:- In this post, we have provided the answers to the NPTEL Project Management For Managers Week 10. All the answers are provided here on the basis of data available on the internet.
NPTEL Project Management For Managers Week 10 Assignment Answers 2022
Q1. In PERT, the distribution of an activity time is assumed to be:
- Normal distribution
- Gamma distribution
- Beta distribution
- Exponential distribution
Answer:- Beta distribution
Q2. The latest start time can be regarded as
- LFT – duration of activity
- LFT + duration of activity
- EFT – duration of activity
- EFT + duration of activity
Answer:- LFT - duration of activity
Q3. Which of the following statement is false in crashing networks?
- Direct cost decreases as project duration decreases
- Direct cost increases as project duration decreases
- Direct cost decreases as project duration increases
- Direct cost increases as project duration increases
Answer:- Direct cost increases as project duration decreases
Q4. An act (i, j) as critical if and only if
- Total float = 0
- Free float = 0
- Independent float = 0
- All of the above
Answer:- All of the above
Q5. In a PERT network, the slack of an event is the difference between:
- Latest occurrence time and earliest occurrence time
- Latest occurrence time and earliest finish time
- Earliest occurrence time and latest occurrence time
- Earliest occurrence time and latest finish time
Answer:- Latest occurrence time and earliest occurrence time
Q6. In the CPM network critical path denotes the
- Path where maximum resources are used
- Path where minimum resources are used
- Path where delay of one activity prolongs the duration of completion of a project
- Path that gets monitored automatically
Answer:- Path where delay of one activity prolongs the duration of completion of a project
Q7. The earliest finish time can be regarded as
- EST + duration of activity
- EST – duration of activity
- LFT + duration of activity
- LFT – duration of activity
Answer:- EST + duration of activity
Q8. The essential condition for the decompression of an activity is:
- The project time should change due to decompression
- After decompression the time of an activity invariably exceeds its normal time
- An activity could be decompressed to the maximum extent of its normal time
- None of the above
Answer:- An activity could be decompressed to the maximum extent of its normal time
Q9. Crashing of a project is the process of reducing the _________________________ of the project?
- Cost
- Time
- Material
- Labor
Answer:- Time
Q10. Float is used for __________.
- Activities
- Events
- Nodes
- None of the above
Answer:- Activities
Important Links:-
NPTEL Project Management For Managers Week 10 Assignment Answers:- In this post, we have provided the answers to the NPTEL Project Management For Managers Week 10. All the answers are provided here on the basis of data available on the internet.