Q1. The relationship between the shape of population distribution and the shape of the sampling distribution of mean is called? 

  • Mean distribution
  • Central limit theorem 
  • Beta distribution
  • Population distributions
Answer:- Central limit theorem

Q2. ____________ is the maximum delay possible for an activity without considering any delay in its precedence or succeeding activity. 

  • Free float
  • Total float
  • Continuous float
  • Independent float
Answer:- Total float

Q3. In an activity has Zero slack, it implies that 

  • It lies on the critical path
  • It is a dummy activity
  • The project is progressing well 
  • None of the above 
Answer:- It lies on the critical path

Q4. Fulkerson’s rule is connected with which of the following.

  • Numbering of events in PERT/CPM 
  • The simulating model
  • Queuing theory 
  • None of the above 
Answer:- Numbering of events in PERT/CPM 

Q5. If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to: 

  • 14 weeks 
  • 18 weeks 
  • 56 weeks
  • 40 weeks
Answer:- 18 weeks 

Q6. Which of the following floats can have a negative value? 

  • Total float
  • Free float
  • Continuous float
  • Independent float
Answer:- Independent float

Q7. What is the additional time available for the performance of an activity in PERT and CPM calculated on the basis that all activities will start at their earliest start time, called? 

  • Slack
  • Total float
  • Free float
  • Independent float
Answer:- Free float

Q8. What is the correct sequence for floats? 

  • Independent float< Total float < Free float
  • Total Float <= Free Float <= Independent Float
  • Independent Float <= Free Float<= Total Float 
  • Free Float < Total Float < Independent Float
Answer:- Independent Float <= Free Float<= Total Float 

Q9. A dummy activity is used in the PERT network to: 

  • Facilitate computation of slacks 
  • Satisfy precedence requirements
  • Determine project completion time
  • Avoid the use of resources
Answer:- Satisfy precedence requirements

Q10. According to the Central Limit Theorem, the mean of a sample is ________ to the mean of a population. 

  • Equal
  • Less than
  • Greater than 
  • Not related 
Answer:- Equal