Q1. For the effective project teams one should have
- Clear sense of mission
- Cohesiveness
- Trust and result oriented
- All of the above
Answer:- All of the above
Q2. What are the reasons behind the failure of the team
- Unclear goals
- Poor communication
- Dysfunctional behavior
- All of the above
Answer:- All of the above
Q3. Which of the following statement is incorrect for critical path method (CPM)?
- The time durations are deterministic.
- Looping and probabilistic events are not allowed in the network.
- It gives the most economical schedule for the projects with fixed duration.
- There is expected duration of the project.
Answer:- There is expected duration of the project.
Q4. The shortest possible time in which an activity can be achieved under ideal circumstances is known as ________
- Pessimistic time estimate
- Optimistic time estimate
- Expected time estimate
- The most likely time estimate
Answer:- Optimistic time estimate
Q5. The performance of a specific task in CPM is known as
- Dummy
- Event
- Activity
- Contract
Answer:- Activity
Q6. Which of the following statements is not correct about PERT?
- Network is constructed based on the events.
- It does not take uncertainties involved in the estimation of times.
- Network deals with uncertainties and hence three time estimations are considered.
- As there is no certainty of time, activity duration cannot be reduced.
Answer:- It does not take uncertainties involved in the estimation of times.
Q7. Choose the correct statement. Dummy activity on a PERT/CPM chart means, it —- ?
- Consumes time, but no resources
- Consumes resources but no time
- Consumes neither time nor resources
- Consumes both resources and time
Answer:- Consumes neither time nor resources
Q8. Pick up the incorrect statement from the following?
- An activity of the project is denoted by an arrow on the network
- The tail of the arrow indicates the end of the activity
- The head of the arrow indicates the end of the activity
- The arrows are drawn (to scale from) left to right
Answer:- The arrows are drawn (to scale from) left to right
Q9. In the network, one activity may connect any —- nodes.
- One
- Two
- Three
- Any number of
Answer:- Two
Q10. In a network diagram an event is denoted by the symbol —-
- Arrow
- Straight line
- Curve
- Circle
Answer:- Circle