NPTEL Project Management For Managers Week 7 Assignment Answers

NPTEL Project Management For Managers Week 7 Assignment Answers:- In this post, we have provided the answers to the NPTEL Project Management For Managers Week 7. All the answers are provided here on the basis of data available on the internet.

NPTEL Project Management For Managers Week 7 Assignment Answers 2022

Q1. For the effective project teams one should have

  • Clear sense of mission
  • Cohesiveness
  • Trust and result oriented
  • All of the above
Answer:- All of the above

Q2. What are the reasons behind the failure of the team

  • Unclear goals
  • Poor communication
  • Dysfunctional behavior
  • All of the above
Answer:- All of the above

Q3. Which of the following statement is incorrect for critical path method (CPM)?

  • The time durations are deterministic.
  • Looping and probabilistic events are not allowed in the network.
  • It gives the most economical schedule for the projects with fixed duration.
  • There is expected duration of the project.
Answer:- There is expected duration of the project.

Q4. The shortest possible time in which an activity can be achieved under ideal circumstances is known as ________

  • Pessimistic time estimate
  • Optimistic time estimate 
  • Expected time estimate
  • The most likely time estimate
Answer:- Optimistic time estimate

Q5. The performance of a specific task in CPM is known as

  • Dummy
  • Event
  • Activity
  • Contract
Answer:- Activity

Q6. Which of the following statements is not correct about PERT?

  • Network is constructed based on the events.
  • It does not take uncertainties involved in the estimation of times.
  • Network deals with uncertainties and hence three time estimations are considered.
  • As there is no certainty of time, activity duration cannot be reduced.
Answer:- It does not take uncertainties involved in the estimation of times.

Q7. Choose the correct statement. Dummy activity on a PERT/CPM chart means, it —- ?

  • Consumes time, but no resources
  • Consumes resources but no time
  • Consumes neither time nor resources
  • Consumes both resources and time
Answer:- Consumes neither time nor resources

Q8. Pick up the incorrect statement from the following?

  • An activity of the project is denoted by an arrow on the network
  • The tail of the arrow indicates the end of the activity
  • The head of the arrow indicates the end of the activity
  • The arrows are drawn (to scale from) left to right
Answer:- The arrows are drawn (to scale from) left to right

Q9. In the network, one activity may connect any —- nodes.

  • One
  • Two
  • Three
  • Any number of
Answer:- Two

Q10. In a network diagram an event is denoted by the symbol —-

  • Arrow
  • Straight line
  • Curve
  • Circle
Answer:- Circle

Important Links:-

NPTEL Answers

Join Our Telegram

NPTEL Project Management For Managers Week 7 Assignment Answers:- In this post, we have provided the answers to the NPTEL Project Management For Managers Week 7. All the answers are provided here on the basis of data available on the internet.

Leave a Comment